About the Evacuation Voltage Optimizer
Evacuation voltage selection determines the appropriate grid voltage level for connecting a solar plant — matching the plant's capacity to the nearest substation's available voltage level and ensuring that the grid can handle the plant's full output without overloading.
How to calculate it
- 1Match capacity to voltage level: up to 1 MW → 11 kV; 1–50 MW → 33 kV; 50–400 MW → 132/220 kV; > 400 MW → 400/765 kV.
- 2Check substation capacity: available import capacity at the target substation must be ≥ plant output × 1.15.
- 3Check line capacity: the 11 kV or 33 kV line from plant to substation must be rated for the plant's fault current; line length affects voltage regulation.
- 4For net metering (< 1 MW rooftop): 415 V LT or 11 kV HT connection depending on plant size and DISCOM preference.
- 5For captive/group captive plants: evacuation voltage is determined by the captive consumer's existing connection voltage.
Worked example
A 5 MWp ground-mount plant in Rajasthan: 33 kV is the correct evacuation voltage. The nearest 33 kV substation is 4 km away. DISCOM capacity check shows 3 MW available on the feeder — insufficient for 4 MW export. Options: (1) upgrade the substation feeder, (2) connect to the 132 kV substation 8 km away.
What you can calculate
- Voltage class
- CEA 2023
- Line loss <3%
- Line current
Frequently asked questions
What is the grid connectivity process for a solar plant in India?
For plants above 1 MW: the developer applies to the state DISCOM or SLDC for a connectivity study. The DISCOM/SLDC assesses the grid's capacity to absorb the plant's output without violating voltage or thermal limits. If adequate, a connectivity agreement is signed. If not, the developer funds grid augmentation or curtails output. This is governed by CERC's Connectivity and General Network Access Regulations (2022).
What is the difference between connectivity and long-term access (LTA)?
Connectivity grants the right to physically connect to the grid. Long-Term Access (LTA) grants the right to use a specific transmission corridor for 25 years to transmit power from the plant to a load centre or exchange. LTA is required for plants selling power under PPAs to state DISCOMs or on power exchanges. Without LTA, a connected plant may face congestion and curtailment if the corridor is used by others.
Ready to build your solar project?
Get free quotes from verified EPCs and installers across India.
You might also need
Step-Up Transformer Sizing
Calculate MVA rating, standard IS 2026 size, impedance and loss budget for solar grid step-up transformers
OpenTransformer Impedance & Losses
Calculate transformer impedance voltage, no-load/load losses and efficiency per IEC 60076
OpenPSS Busbar Sizing
Size substation busbars for continuous current, thermal limits and short-circuit withstand per IS 5082
OpenCT Sizing & Class Selection
Select current transformer ratio, accuracy class and knee-point voltage for protection and metering per IEC 61869
OpenPT / CVT Selection
Select voltage transformer or capacitor voltage transformer class, burden and accuracy for HV/EHV systems
OpenCircuit Breaker Rating
Rate circuit breakers for fault interrupting capacity, rated voltage and operating duty per IEC 62271
Open