About the Control Room Area Estimator
Solar substation control room area sizing determines the minimum floor space required to house the SCADA / RTU cabinets, numerical protection relay panels, DC battery bank, and ancillary equipment — based on CEA norms, panel dimensions, and operational clearance requirements.
How to calculate it
- 1List all equipment to be housed: relay panels (HV feeder, transformer differential, bus protection), SCADA/RTU rack, DC distribution board (DCDB), battery charger and 110 V DC battery bank, communication equipment (router, optical terminal), metering panel, and earthing bar.
- 2Assign standard panel widths: relay panels typically 600–800 mm wide; SCADA rack 600–800 mm; battery bank requires a separate ventilated battery room or bay.
- 3Apply CEA clearances: 1500 mm front-of-panel working aisle; 800 mm rear-of-panel maintenance aisle; 600 mm between panel rear and wall if no access required.
- 4Layout panels along one or two rows, calculate total length, and multiply by aisle depth to get the net floor area.
- 5Add 20% for cable entry space (raised floor plenum or cable trench) and future panel slots.
Worked example
A 33 kV, 10 MW solar plant: 4 relay panels (3.2 m), 1 SCADA rack (0.8 m), 1 DCDB + charger (0.8 m) = 4.8 m row length. Front aisle: 1.5 m. Panel depth: 0.6 m. Rear aisle: 0.8 m. Net control room width: 1.5 + 0.6 + 0.8 = 2.9 m. Length: 4.8 m + 1 m for access = 5.8 m. Control room area ≈ 5.8 × 2.9 = 16.8 m². Add 20% → ~20 m² minimum. Provide separate battery room (4 × 3 m = 12 m²) with ventilation.
What you can calculate
- Panel count
- SCADA consoles
- NBC clearance
- Cable trench
Standards & references
Frequently asked questions
Can the battery bank be kept in the same room as the relay panels?
It is not recommended. Lead-acid batteries off-gas hydrogen during charging; IS 1554 and CEA norms require a separate ventilated battery room or a sealed VRLA battery cabinet. Lithium-ion batteries (increasingly used for 110 V DC substation supplies) off-gas less but still require a temperature-controlled environment and fire detection. Keeping batteries away from the relay room also eliminates the risk of battery acid vapour corroding relay panel contacts.
Ready to build your solar project?
Get free quotes from verified EPCs and installers across India.
You might also need
Step-Up Transformer Sizing
Calculate MVA rating, standard IS 2026 size, impedance and loss budget for solar grid step-up transformers
OpenTransformer Impedance & Losses
Calculate transformer impedance voltage, no-load/load losses and efficiency per IEC 60076
OpenPSS Busbar Sizing
Size substation busbars for continuous current, thermal limits and short-circuit withstand per IS 5082
OpenCT Sizing & Class Selection
Select current transformer ratio, accuracy class and knee-point voltage for protection and metering per IEC 61869
OpenPT / CVT Selection
Select voltage transformer or capacitor voltage transformer class, burden and accuracy for HV/EHV systems
OpenCircuit Breaker Rating
Rate circuit breakers for fault interrupting capacity, rated voltage and operating duty per IEC 62271
Open