About the Plant Loss Breakdown
Plant Loss Breakdown (or energy waterfall) maps every loss between the solar resource striking the array and the net energy exported to the grid — following the IEC 61724 chain: irradiation → DC generation → inverter losses → AC losses → transformer losses → net energy. It tells you where your plant is losing value and what fixing each loss stage would recover.
Formula
PR = E_AC ÷ (H × P_STC)
- E_AC
- Net AC energy exported (kWh)
- H
- In-plane irradiation (kWh/m²)
- P_STC
- Array DC nameplate capacity (kWp)
How to calculate it
- 1Start with gross irradiation (GHI) and apply tilt/azimuth correction to get in-plane irradiation.
- 2Apply soiling loss (2–15% depending on location and cleaning frequency).
- 3Apply temperature loss (0.3–0.4%/°C above 25°C; typically 5–12% annual average in India).
- 4Apply shading and row-to-row losses (0–5% depending on row spacing and obstructions).
- 5Apply mismatch loss (0.5–2%) and wiring/DC loss (<1% for well-designed systems).
- 6Apply inverter efficiency loss (typically 2–4% for string inverters including MPPT and conversion).
- 7Apply transformer and AC cable losses (0.5–2%).
- 8The remaining energy is net AC generation. The ratio of net AC to irradiation × nameplate is the PR.
Worked example
A 1 MWp plant in Rajasthan: gross GHI 2,100 kWh/m²/yr, in-plane 2,200 kWh/m². Losses: soiling 5%, temperature 8%, shading 1%, mismatch 1%, DC wiring 0.5%, inverter 3%, transformer 1.5% → PR ≈ 80.5%. Net generation = 2,200 × 1,000 × 0.805 = 17.7 L kWh/year.
What you can calculate
- 9-step waterfall
- Net PR
- Loss per stage
- IEC 61724
Standards & references
Key definitions
Definitions from the SolarPedia glossary
Frequently asked questions
What is a good performance ratio (PR) for a solar plant in India?
A well-designed, well-maintained solar plant in India achieves a PR of 78–84%. Values above 84% are exceptional (usually tracker-mounted plants in low-temperature, low-soiling sites). Below 75% typically indicates a systemic issue — heavy soiling, shading, or an undersized inverter. Monthly PR monitoring is the fastest way to catch underperformance.
Which loss category is typically the biggest in Indian solar plants?
Temperature loss is usually the largest single loss category (6–12% annually) in most Indian locations, followed by soiling (3–15% depending on cleaning frequency and location). In poorly designed systems, shading can also be large. The waterfall model makes it easy to rank losses and prioritise O&M interventions.
How do I improve my plant's PR?
The highest-ROI interventions are usually: (1) increase cleaning frequency in dusty sites, (2) check and replace underperforming modules (hotspot/PID), (3) verify inverter settings and MPPT health, (4) fix loose DC connections that cause resistive losses. A 1-percentage-point PR improvement on a 1 MW plant at ₹7/kWh saves roughly ₹1.5 L/year.
Ready to build your solar project?
Get free quotes from verified EPCs and installers across India.
You might also need
Energy Generation
Calculate daily, monthly, and annual generation from kWp, PSH, and PR with revenue projection
OpenPerformance Ratio (PR)
Calculate IEC 61724 performance ratio from actual vs theoretical generation and grade the result
OpenCUF / PLF Calculator
Calculate Capacity Utilisation Factor and Plant Load Factor with India state-wise benchmarking
OpenTemperature Loss
Quantify power derating from cell temperature using NOCT model per IEC 61215
OpenShading Loss
Estimate annual energy and revenue lost due to near and far shading obstructions
OpenDegradation & Aging
Project 25-year plant performance with annual degradation and warranty compliance check
Open